Wednesday, September 06, 2006

Progress on the Millers Run Project

John Richards has an article in today's O-R about the Millers Run Sewerage Project in Cecil Township. Most of John's report focuses on news of the bonds to fund the project but he ends with this note on when work will begin:

Edward T. Sitarik Contracting and A. Merante Contracting are scheduled to begin on the sewer lines along Route 50 and interceptor by mid-September. Work on the pump station and treatment plant should begin by late September or early October, Bell said.